U212 NFS submarines
ItalyItalian Navy / OCCAR / Fincantieri
The first U212 NFS submarine's keel was laid in February 2026. The Navy's March update targets initial deliveries from 2029.
Latest dated record: 23 Jul 2026 · Reviewed 3 Oct 2026
A total programme budget has not been established from the listed sources. IOC means initial operational capability; a flight or delivery target may refer to a different milestone.
Timeline
Confirmed records describe reported events. Targets are announcements and remain targets until a source confirms completion.
- 27 Feb 2026Confirmed record
First submarine keel was laid.
Source announcement ↗ - 23 Jul 2026Confirmed record
Fincantieri announced a contract amendment covering technology and services, with an accelerated delivery schedule.
Source announcement ↗ - 2029Announced target
Initial submarine deliveries are planned to begin.
Source announcement ↗ - 2032Announced target
The fourth boat is now targeted for delivery in 2032, with annual deliveries intended from 2029.
Source announcement ↗
Open questions & dependencies
- Delivery, crew preparation and operational acceptance are separate milestones.
- The planned first-delivery year is not entered as a confirmed IOC.
Sources
- Italian Navy: U212 NFS first keel laidPublished 10 Mar 2026
- Fincantieri: U212 NFS contract amendment and delivery schedulePublished 23 Jul 2026